RDSS Scheme and Underground Cabling – A Survey Guide
What the Revamped Distribution Sector Scheme pays for, where underground cabling sits among its loss reduction works, and how contractors plan the route survey on an RDSS package.
₹24/m standard₹32/m L-sectionMin 4 km · GST extra
- STEP 1List sanctioned cable works
- STEP 2Measure route kilometres
- STEP 3Scan and mark services
- STEP 4Hand over survey records
The RDSS scheme is the Government of India's Revamped Distribution Sector Scheme, with an outlay of ₹3,03,758 crore, to cut DISCOM losses and improve supply. It funds smart metering and distribution infrastructure works. Where those works include underground cabling, RMUs or new substations, contractors survey existing services with GPR before digging.
- RDSS was approved in 2021 with ₹97,631 crore of central support towards a ₹3,03,758 crore outlay.
- Its targets are pan-India AT&C losses of 12–15% and closing the gap between supply cost and revenue.
- Funds go to smart metering and to loss reduction and modernisation works proposed by each DISCOM.
- Underground cabling, RMUs and substations appear in some sanctioned works, especially in dense or coastal areas.
- Any RDSS work that digs into streets benefits from a GPR survey of existing services first.
Updated:

What is the RDSS scheme?
The RDSS scheme, or Revamped Distribution Sector Scheme, is a central government programme to make power distribution companies financially sound and operationally efficient. The Cabinet Committee on Economic Affairs approved it on 30 June 2021 (Power Line, July 2021). The Ministry of Power lists an outlay of ₹3,03,758 crore, including gross budgetary support of ₹97,631 crore from the Centre.
Its two headline targets are to bring aggregate technical and commercial (AT&C) losses down to 12–15% across India and to close the gap between the average cost of supply and the average revenue realised (ACS-ARR gap). The scheme period was set as FY 2021-22 to FY 2025-26. In 2025 the Ministry of Power sought a two-year extension (Energetica India, March 2025), so check the current timeline with the RDSS portal or your DISCOM before planning around it.
How does the revamped distribution sector scheme work?
RDSS is results-linked. A DISCOM prepares proposals, meets pre-qualifying criteria and is evaluated each year against an agreed plan; release of funds depends on that performance. REC Ltd and Power Finance Corporation (PFC) act as nodal agencies, sanctioning projects and monitoring progress.
Part A – metering
Prepaid smart meters for consumers and system meters on feeders and distribution transformers, so energy can be accounted for at each level.
Part A – infrastructure works
Loss reduction works and modernisation of the network, proposed by each DISCOM in its project reports. Central grant for these works is up to 60% of the approved cost, and up to 90% for special category states (Power Line, July 2021).
Part B – training and capacity building
Training, consultancy and enabling activities that help utilities carry out reforms.
Where does RDSS underground cabling fit among DISCOM loss reduction works?
Each DISCOM chooses its own mix of works for its network. Common DISCOM loss reduction works and modernisation items include:
- aerial bunched cable in place of bare LT conductors, to curb hooking;
- high voltage distribution system (HVDS) conversion, using smaller transformers closer to consumers;
- feeder bifurcation and agricultural feeder segregation;
- new or augmented substations and distribution transformers;
- underground cabling with ring main units in dense or vulnerable areas;
- SCADA and distribution management systems in urban centres.
RDSS underground cabling is not universal. Trade reports note that disaster-resilient works sanctioned for some coastal regions include underground cabling, ring main units and aerial bunched cable (T&D India). Whether your package includes buried cable depends entirely on the sanctioned project report.
Of these works, underground cabling, RMU and substation plinths, transformer foundations and new pole or HVDS foundations all involve excavation in public ground. Those are the items where a survey of existing services matters.
What does an RDSS cabling package look like on the ground?
A typical turnkey package bundles many small works across several towns of one circle or division. In a city it might hold a few kilometres of 11 kV cable along municipal roads, RMUs at feeder junctions, plinths for new transformers and short LT cable runs to feeder pillars. In rural areas the same package may hold HVDS points, feeder segregation and new poles, with little cable at all.
For survey planning, this means two kinds of job sit side by side: linear routes measured in kilometres, and point sites such as plinths and foundations. Both need scanning before digging, but they are counted differently. Many work fronts also run at once, so the survey has to be organised division by division, not as one long route.
Which RDSS terms should a cabling contractor know?
- AT&C loss: the share of energy input not billed or not paid for, combining technical losses and commercial losses such as theft.
- ACS-ARR gap: the difference between what a unit of power costs the DISCOM and what it earns per unit.
- DPR: detailed project report setting out the works a DISCOM proposes for sanction.
- GBS: gross budgetary support, the central grant share.
- Special category states: north-eastern states and certain hill and island regions eligible for a higher grant share.
- Nodal agency: REC or PFC, which sanction and monitor projects.
- Turnkey contract: a package in which one contractor delivers design, supply, installation and commissioning.
How should a contractor plan the survey on an RDSS package?
- Read the sanctioned scope. List every work that needs digging: cable routes, RMU and substation sites, transformer plinths and new foundations.
- Measure lengths and sites. Add up route kilometres per circle or division, and list point sites separately.
- Mark the crossings. Road, drain, canal and rail crossings need extra scanning and may be bored.
- Decide on L-section. Check whether the DISCOM's specification asks for a depth profile along any route.
- Price the whole order. One order covering several divisions can cross a discount slab that separate orders would miss. Our guide to survey quantity in a DISCOM tender BOQ explains the method.
- Phase the field work. Keep survey crews a few days ahead of excavation in each division.
Why survey before digging on RDSS works?
RDSS packages often run on tight programmes across many towns at once. A single strike on a water main or telecom duct can stop a work front for days, bring claims and draw complaints from the road owner. Ground penetrating radar (GPR) scanning across each route and site shows underground utilities such as existing pipes, ducts and cables, while a cable locator singles out energised ones. Marks on the ground then guide the excavation gang.
The survey is most valuable before cable routes and plinth positions are frozen, so the design can avoid conflicts. Radar reach depends on the soil and on moisture, and a careful report states it for each section. For trenched and drilled cable works alike, read the scope under HT/LT cable route GPR survey, while the power utilities page explains what DISCOM engineers look for in survey records. Where the package is mainly a conversion from overhead lines, our overhead to underground conversion guide goes into that work.
What survey records help at RDSS measurement and audit?
Results-linked schemes are measured and checked closely, so tidy records pay off.
- Survey report per division, using the same work names as the sanctioned DPR.
- Daily log of metres scanned, signed by the site engineer where possible.
- Ground-marking photographs at crossings and equipment sites.
- Notes on stretches where radar reach was limited, with any trial pit confirmation.
- As-laid data in the format the DISCOM's GIS needs.
Drawing sets and GIS layers can be prepared through our CAD and GIS utility mapping service as a separately quoted item. Mezux Touch has no affiliation with REC, PFC, the Ministry of Power or any DISCOM. Our client is the contractor or owner that commissions the survey.
Bidding for an RDSS cabling package?
With 58 GPR systems of its own and survey staff on its payroll, Mezux Touch can open several RDSS work fronts from its Faridabad base. Scanning a route is charged at ₹24 a metre; where an L-section profile is specified, the figure is ₹32. Each order bills a minimum of 4 km; outside Delhi NCR a ₹1,00,000 project floor applies. Whole-order discounts start once a package passes 100 km. GST, mobilisation, night shifts, traffic arrangements and drawing sets are added separately. Test your package length on the GPR survey price list calculator, then send the scope through the quote form.
More guides on DISCOM programmes and cable surveys
Questions about RDSS and underground cabling
Does RDSS pay for underground cabling?
It can, where a DISCOM proposes underground cabling within its sanctioned loss reduction or modernisation works. Trade reports mention underground cabling and RMUs among sanctioned works for some coastal areas. Whether a particular town is covered depends on the DISCOM's approved project report.
Who are the nodal agencies for RDSS?
REC Ltd and Power Finance Corporation (PFC). They sanction DISCOM projects, release funds and monitor physical and financial progress on behalf of the Ministry of Power. Contractors deal with the DISCOM that awards their package, not directly with the nodal agencies.
Is the GPR survey a separate item in RDSS tenders?
That depends on how the DISCOM frames its tender. Some list survey as its own BOQ line; others include it within route preparation. Read the specification carefully and price survey length, L-section metres and drawings explicitly.
Can Mezux help a DISCOM get RDSS approval?
No. Mezux Touch has no role in RDSS sanction, approval or funding, and no affiliation with REC, PFC, the Ministry of Power or any DISCOM. We provide GPR route surveys to contractors and owners carrying out the works.
Has the RDSS deadline been extended?
The original period ended in FY 2025-26. Reports in 2025 said the Ministry of Power had sought a two-year extension to FY 2027-28. Check the latest position on the official RDSS portal or with your DISCOM before relying on any date.
Which RDSS works need a survey of existing services?
Any work that excavates public ground: underground cable routes, RMU and compact substation plinths, transformer foundations, new pole or HVDS foundations and earthing pits. Metering-only work rarely needs one, since meters are fixed above ground on existing connections.
Cable route survey by city
- Ground penetrating radar survey in Delhi
- Cable and pipe detection in Mumbai
- GPR survey in Bengaluru
- Chennai GPR survey
- GPR survey company in Hyderabad
- Underground utility survey in Kolkata
- Ground penetrating radar survey in Pune
- Cable and pipe detection in Ahmedabad
- GPR survey in Gurugram
- Noida GPR survey
- GPR survey company in Jaipur
- Underground utility survey in Lucknow
- Ground penetrating radar survey in Indore
- Cable and pipe detection in Bhopal
- GPR survey in Patna
- Chandigarh GPR survey
- GPR survey company in Nagpur
- Underground utility survey in Kochi
- Ground penetrating radar survey in Guwahati
- Cable and pipe detection in Bhubaneswar
Survey services for distribution contractors
- Fibre network construction
- Sub-surface void survey of roads
- OFC route GPR survey
- Underground mapping for smart cities
- Corridor utility survey
- Telecom underground survey
- Turnkey utility survey for EPC
- Road-cutting permission support
- Underground utility mapping services
- Gas pipeline route survey
- Road widening utility survey
- GPR survey cost in India
- GPR survey for metro rail
- Highway crossing survey
- HT/LT underground cable mapping
- Site scan before excavation
- Sewer network survey
- Void & cavity detection
- Utility strike prevention survey
- DISCOM cable network survey
Send your RDSS package scope
What to send for an exact quote
- The alignment as KML, drawing or road list
- Town and type of site – public road, estate or plant
- Whether the scope needs an L-section
- Preferred start date and any night-only stretches
Minimum 4 km · GST extra · ₹1,00,000 project minimum outside Delhi NCR · 25–50% off above 100 km.
What happens next
- Scope check – we confirm route length, crossings and L-section need.
- Written quote – rate, slab, minimums, extras and a day-by-day programme.
- Mobilisation – our own crew and systems on the agreed date.