Survey guide — OH to UG conversion
Overhead to Underground Cable Conversion – Planning the Survey
Why Indian towns are taking power lines off poles, what a conversion project replaces on the ground, and how the underground survey is planned so new cables avoid old services.
₹24/m standard₹32/m L-sectionMin 4 km · GST extra
- STEP 1Collect feeder and pole data
- STEP 2Scan lanes and crossings
- STEP 3Layer services on map
- STEP 4Release cleared sections
Overhead to underground conversion replaces pole-mounted HT and LT lines with buried cable, and pole transformers with ground-mounted units, feeder pillars and new service cables. DISCOMs do it for safety, reliability and lower losses. Because new trenches enter crowded streets, a GPR survey of existing services is planned before design and digging.
- Conversion moves HT, LT and service lines below ground and removes the poles they hung on.
- Safety, storm resilience, fewer outages and harder power theft are the usual reasons cities convert.
- Each house connection, transformer and street crossing becomes underground work in already crowded lanes.
- Survey ahead of design lets routes, pillars and RMUs be placed clear of existing pipes and ducts.
- Records from the survey and as-laid work become the utility's first reliable underground network map.
Updated:

What is overhead to underground conversion?
Overhead to underground conversion is the replacement of a distribution network that hangs on poles with one buried in the ground, and it is among the largest changes a power distribution network can go through. In a typical Indian town that covers 11 kV feeders, LT distribution lines, street-light circuits and the service drops to individual buildings. Once the cables are in and commissioned, the old conductors and most poles are removed.
The equipment changes as well. A transformer that sat on a pole platform moves to a ground-mounted plinth or a compact substation. Overhead switches give way to ring main units, and LT distribution boxes become feeder pillars. Each house is then reconnected through an underground service cable. In effect, converting an overhead line to underground cable means rebuilding the local network rather than simply lowering wires.
Which parts of the network change in a conversion?
Scope varies by tender, but four layers of the network are usually involved, each with its own ground needs.
HT feeders
11 kV lines between the substation and transformers become XLPE cables in trenches or ducts, joined through ring main units that let supply be rerouted around a fault.
LT distributors
The 415 V lines along streets become LT cables running from each transformer to feeder pillars, which split supply towards groups of buildings.
Service connections
Each consumer's overhead drop becomes a small underground cable from a pillar or distribution box to the meter. In dense lanes this is the largest number of individual excavations.
Street lighting and others
Street-light circuits are often moved underground at the same time, and some projects add ducts for telecom operators that shared the poles.
Why are DISCOMs moving lines underground?
- Safety. Snapped conductors, low-hanging wires and contact with buildings cause accidents; buried cable removes most of that exposure.
- Storms and cyclones. Trees and wind bring down overhead lines. Coastal utilities in particular have put resilient underground networks into their plans.
- Fewer outages. Bird faults, kite strings and tree contact disappear, although a cable fault, when it happens, takes longer to find.
- Lower losses. Hooking onto bare overhead conductors becomes far harder, which supports the loss-reduction targets utilities work towards.
- Space and appearance. Pole removal frees footpaths and improves heritage, market and tourist areas.
Funding often comes through national distribution programmes. The current one is described in our guide to the RDSS scheme and underground cabling. State budgets and city projects pay for other conversions.
How does a UG cabling project run from start to finish?
Every DISCOM underground cabling package differs in detail, but the order of work is broadly similar.
- Network study. The utility fixes the area, feeders and loads to be converted, and the voltage levels involved.
- Survey. Existing underground services are located along proposed routes and at planned equipment sites.
- Design. Cable routes, RMU and transformer plinths, feeder pillar positions and crossings are drawn on the surveyed base.
- Permissions. Right of way and road-cutting consent are obtained from municipal bodies, development authorities and other road owners.
- Civil and cable work. Trenches and bores are made, ducts and cables laid, and equipment foundations built.
- Cutover. Consumers are moved from overhead to underground supply in planned shutdowns, area by area.
- Dismantling and reinstatement. Old conductors and poles come down, and roads and footpaths are restored.
Which terms are used in conversion tenders?
- OH to UG: short form for overhead-to-underground work.
- Cutover: switching consumers from the old overhead supply to the new cable network.
- Shutdown: a planned outage needed for cutover, jointing or dismantling.
- Compact or package substation: a ground-mounted enclosure combining switchgear, transformer and LT panel.
- Service cable: the small LT cable from a feeder pillar or distribution box to a consumer's meter.
- Aerial bunched cable (ABC): insulated conductors twisted together on poles, an overhead alternative where full undergrounding is not taken up.
- Reinstatement: restoring road and footpath surfaces after excavation.
What makes conversion harder than a new cable route?
A new feeder can often pick a quiet verge. A conversion has no such freedom, because it must reach every pole position, every transformer and every house the overhead network served. That pushes trenches into old bazaars, narrow lanes and residential streets where water pipes, sewers, gas lines and telecom ducts were laid long before anyone planned for power cable.
Equipment needs ground space too. An RMU, compact substation or feeder pillar needs a plinth on land the utility can use, often a small corner of a footpath that is already full of services. Our guide to RMU and feeder pillar cables looks at those sites in detail. Lastly, cutover has to keep consumers on supply, so work is phased and sometimes squeezed into night hours.
When should the GPR survey happen on a conversion project?
Before design, wherever possible. If the cable route and plinth positions are drawn first and surveyed later, conflicts found on site force redesign while gangs wait. Ground penetrating radar (GPR) run along and across each lane picks up pipes, ducts, cables and other underground utilities as reflections, and an EM cable locator picks out live conductors. Results are marked on the ground and written into a report that designers use to place the new network.
On large packages, the survey is phased to stay ahead of the trench gangs, division by division. How deep the radar sees varies with soil type and wetness, which is why the report gives a limit for each stretch. Scope details are on the HT/LT cable route GPR survey page, the power utilities page covers what DISCOM teams expect, and our BOQ guide for DISCOM tenders explains how to size the survey quantity. We hold no DISCOM affiliation or utility approval of any kind; our crews work under the contract of whoever commissions the survey.
How are plinth sites and house connections handled in the survey?
Linear routes are only part of a conversion. Every proposed RMU, compact substation, transformer plinth and feeder pillar is a point site that needs its own close-spaced scan, because cables and pipes there run in several directions. Sites are best checked as candidates, so the designer can pick the clearest one.
Service connections are harder to survey individually, since there may be hundreds in a single ward. A practical approach is to scan the footpath strip along each street where service cables will branch off, then rely on marking and careful hand-digging for the short final runs to each building. Water service pipes and gas connections are the services most often met on those short runs, so crews should expect them at every property line.
How should records be kept after conversion?
Many towns gain their first true underground power map from a conversion project, and that record is worth protecting.
- Combine survey findings with as-laid cable routes, depths, joints and crossings.
- Tie every RMU, substation and feeder pillar to the feeder it belongs to.
- Record which consumers each pillar serves, so faults can be traced quickly.
- Keep the data in a format the utility's GIS can import.
Our CAD and GIS utility mapping service can prepare survey results in drawing or GIS form, quoted separately from the field survey.
Pricing a conversion package? Start with the survey quantity
Mezux Touch surveys with company-owned GPR systems and its own crews, mobilising from Faridabad. A conversion area is priced by the metre of lane and road scanned: ₹24 for standard survey and ₹32 where an L-section is called for. The minimum bill is for 4 km, projects beyond Delhi NCR carry a ₹1,00,000 floor, and large orders earn whole-order discounts. Mobilisation, night working, traffic management and drawings are quoted on top, and GST is extra. Send your conversion area map through the quote form below.
More guides on DISCOM cabling work
Questions about overhead to underground conversion
Is covered conductor the same as underground conversion?
No. Covered conductor keeps the line on poles but insulates the wire. Underground conversion removes the overhead line and buries cable instead. Many programmes use both: covered conductor on open stretches and underground cable in dense areas.
Do consumers lose supply during conversion?
Only during planned shutdowns for cutover and dismantling. The new network is built alongside the old one while it stays live, then consumers are switched across area by area. Utilities usually announce shutdowns in advance and keep them as short as the work allows.
Does every house need a new service connection?
Yes, in a full conversion. The overhead service drop is replaced by an underground service cable from a feeder pillar or distribution box to the meter, which means a small trench or duct to each building.
Can the survey start before the design is final?
It should. Surveying candidate routes and equipment sites first gives designers a base map of existing services, so the final design avoids conflicts instead of discovering them on site. Late changes to the design can be covered by a short supplementary survey.
Is Mezux an approved vendor for any DISCOM conversion programme?
No. Mezux Touch has no affiliation, approval or empanelment with any DISCOM. Our GPR surveys are commissioned by contractors or owners and delivered under their contracts. Any utility approval of the cabling work itself is a matter between the utility and its contractor.
Who pays for overhead to underground conversion?
Usually the DISCOM, often with central or state programme funding, and sometimes a city body or developer for a specific area. The contractor's survey cost is normally part of the cabling package price, shown as its own BOQ line or included within route preparation.
Conversion area survey by city
- GPR survey company in Delhi
- Underground utility survey in Mumbai
- Ground penetrating radar survey in Bengaluru
- Cable and pipe detection in Chennai
- GPR survey in Hyderabad
- Kolkata GPR survey
- GPR survey company in Pune
- Underground utility survey in Ahmedabad
- Ground penetrating radar survey in Gurugram
- Cable and pipe detection in Noida
- GPR survey in Jaipur
- Lucknow GPR survey
- GPR survey company in Indore
- Underground utility survey in Bhopal
- Ground penetrating radar survey in Patna
- Cable and pipe detection in Chandigarh
- GPR survey in Nagpur
- Kochi GPR survey
- GPR survey company in Guwahati
- Underground utility survey in Bhubaneswar
Survey services for DISCOM contractors
- Buried pipe tracing
- Construction site GPR survey
- Leak zone detection
- HDD crossings under roads
- OFC route GPR survey
- Gas pipeline route survey
- GIS utility mapping agency
- GPR survey cost in India
- Underground power cable tracing
- Utility survey before HDD
- Utility corridor mapping
- HT/LT cable route GPR survey
- EPC utility survey support
- Road & highway GPR survey
- Cavity detection survey
- Telecom route survey
- GPR survey by sector
- Underground mapping for smart cities
- SUE quality-level survey
- GPR scanning services
Send your conversion area for a quote
What to send for an exact quote
- Start and end points of the route, or a KML
- District and site type
- Survey type: standard or L-section
- When you want the crew on site
Minimum 4 km · GST extra · ₹1,00,000 project minimum outside Delhi NCR · 25–50% off above 100 km.
What happens next
- Scope check – we confirm route length, crossings and L-section need.
- Written quote – rate, slab, minimums, extras and a day-by-day programme.
- Mobilisation – our own crew and systems on the agreed date.






