Skip to main content
ISO 9001:2015 · ISO 14001:2015 · ISO 45001:2018

GPR Services

GPR Road and Highway Survey for Utility Mapping

Road corridors carry more buried services in the shoulder than under the carriageway — and a widening package priced without knowing that carries diversion cost as unquantified exposure.

Where the trouble actually is

Not under the carriageway.In the shoulder.In the median.In the land you are about to take.

Decades of utilities were laid alongside roads precisely because it was the easiest available route. Power feeders, water mains, gas transmission, canal siphons and unrecorded legacy telecom all accumulate there, and none of it appears on a road drawing.

Chainage-referenced crossing schedule · Full corridor width · Night working on live carriageways

Quick AnswerMezux Touch carries out GPR road and highway survey across full corridor width — carriageway, shoulder, median and acquisition land — producing a chainage-referenced crossing schedule that a site engineer can work from. Used on widening packages, service road construction and pre-tender utility risk assessment.

Why the survey covers more than the road

A road drawing shows the road. It does not show the power feeder laid along the shoulder in 1994, the irrigation line crossing beneath the median, or the telecom duct installed by an operator who no longer holds the records.

We survey the full corridor width including the land taken for widening, because that is where the findings are and where diversion cost is created. A package priced on carriageway data alone carries the rest as exposure nobody has measured.

What the deliverable actually is

The core deliverable is a crossing schedule keyed to chainage: for each buried line, its type where known, approximate depth, crossing angle and a confidence grade, which a site engineer can carry to the excavation face. It is issued inside a signed report; layered CAD or GIS files are optional, separately quoted items. Lines that cannot be linked to an owner are listed as unattributed, not assigned on a hunch.

Road survey sequence

How a road corridor survey runs

Corridor width, not carriageway width

The surveyed band is set from the acquisition boundary rather than the road edge, because shoulder and widening land carry most of what a package needs to know about.

Lane closures as a programme item

Work on live carriageways runs under a traffic management plan with marshalling and tapers priced as their own line. Night working is normal on high-volume sections rather than exceptional.

Radar and electromagnetic together

Both methods run and are reconciled, because a locator misses non-metallic lines and radar alone struggles where several services run parallel and close.

Layer thickness in the same pass

Where specified, the same radar captures bound course thickness and sub-base condition, which replaces coring on a blind grid with a continuous profile.

Referencing findings so they can be found

Every crossing is tied to chainage rather than to a coordinate alone, since that is how a site engineer locates it with a tape on the day.

Nominating points worth exposing

Critical crossings where a strike would stop the works are nominated for physical verification rather than cleared on detection alone.

Schedule first, drawing second

The crossing schedule is the primary output. Where CAD or GIS files are ordered as a separate item, they support the schedule rather than replace it, because a drawing filed in an office prevents nothing at the excavator.

Answering queries during construction

Questions from site during the works are answered against our own data rather than by referring the client back to the drawing.

Where road surveys go wrong at tender stage

Highway utility mapping specifications routinely omit the one thing that matters most: whether road subsurface investigation is included alongside utility detection, or whether the two are separate scopes. Almost always in the specification. A tender asking for utility survey without stating quality level, deliverable format or who carries the trial-hole obligation produces bids that cannot be compared and a deliverable nobody can use.

We help authorities and consultants write that scope, including on packages we do not eventually bid, because a badly specified survey wastes everyone's money including ours.

NCR road corridors we work

A GPR road survey and a GPR highway survey are the same technique at different scales: a municipal road needs the same crossing schedule a national highway does, but corridor width and traffic management differ. Road utility mapping across either is billed at the same ₹24 per metre; corridor width and traffic management change the programme and the separately charged traffic items, not the metre rate. Arterials, sector roads and expressway approaches across the capital region are surveyed from our Faridabad base. Ground varies enough between these areas to change what a corridor survey can establish:

GPR survey in Rohini|GPR survey in Dwarka|GPR survey in Saket|GPR survey in Gurugram|GPR survey in Noida|GPR survey in Faridabad|GPR survey in Ghaziabad|GPR survey in Greater Noida

Pricing a road widening package?

Send the chainage limits — shoulder and acquisition land usually decide the diversion cost.

Get A Quote +91 99100 10209

Road and highway GPR survey — scope, format and detailed questions

Road corridor surveys fail for a predictable reason: they are scoped to the road rather than to the corridor. Utilities were laid alongside highways because it was the cheapest route available, and the shoulder, median and widening land carry decades of accumulated servicing that appears on no road drawing.

Why the schedule matters more than the drawing

A CAD file sits in a design office. A chainage-referenced schedule goes in the site engineer's hand and tells him what he will meet at 4+250, at what depth and at what angle. Surveys that produce beautiful drawings and no schedule are surveys whose findings never reach the person operating the machine, which is where the value was supposed to be realised.

What is delivered

A chainage-referenced crossing schedule as the primary output, inside a signed report. Layered CAD in your convention or GIS layers for ingestion can be added as separately quoted items. Pavement layer thickness and sub-base condition as a separate profile where in scope, with loss-of-support zones reported as void findings rather than pavement data. Confidence stated per feature, unattributed services reported as unattributed, and critical crossings nominated for verification with the reason given.

Beyond the basics

Why does shoulder land carry so much? Because it was the easiest available route for decades of utilities, and none of those installations appear on a road drawing.

Can radar measure pavement thickness? Yes, including interfaces between courses and zones retaining moisture or having lost sub-base support.

How is a highway survey priced? At ₹24 per metre surveyed, or ₹32 with an L-section, with slab discounts on long orders. Traffic management, night working, mobilisation and drawing sets are listed separately, so the per-metre figure never hides them.

What about crossings under the carriageway? Surveyed from the surface without closure where possible, and nominated for verification where a strike would stop the works.

Do you provide as-built after diversion? Where the diversion is ours, always. Where another party diverts, we can record it before it is covered.

Terms used on this page

Chainage — the running distance along a corridor, used on site to find each logged crossing. Acquisition land — ground taken for widening, carrying utilities absent from road drawings. Sub-base — the layer beneath bound pavement courses, whose condition governs road performance. Unattributed service — a detected line no owner claims, reported as such rather than assigned. Traffic management plan — the closure and marshalling arrangement, a cost and programme item.

Service — Road & Highway GPR Survey
Quick answer

A GPR road and highway utility survey finds buried cables, pipes and ducts in the carriageway, verges, median and land acquired for widening, and logs each crossing by chainage before road works begin. Mezux Touch charges ₹24 per metre, or ₹32 with an L-section; minimum order ₹50,000 in Delhi NCR and ₹1,00,000 elsewhere. GST extra.

Rates and page checked:

Mezux survey crew in safety gear standing beside radar carts
Road crews work behind the traffic arrangement agreed for each stretch.
Diagram of buried services crossing beneath a road carriageway
Each service crossing the carriageway is logged with its chainage and approximate depth.
Workers hand-digging a trench beside a marked buried service
Near a marked line, hand digging replaces the excavator bucket.
CAD drawing showing utility lines plotted along a road alignment
CAD drawing sets for a road corridor are an optional, separately quoted item.
How it works · Road crossings logged by chainage
LT cableWater mainHT cableOFC ductDrainL-SECTION · DEPTH ALONG THE ROUTERoute startRoute end
  1. STEP 1Corridor band agreed
  2. STEP 2Radar and EM sweeps
  3. STEP 3Crossings tied to chainage
  4. STEP 4Schedule handed to site

When does a road project need a GPR road and highway utility survey?

A GPR road and highway utility survey earns its cost wherever road work will cut, bore or pile into ground beside an existing carriageway. Typical triggers:

  • Widening and service roads – the new pavement edge lands on verges that carry feeders, water mains and telecom ducts.
  • Junction and intersection improvements – services from several directions converge under one small area, with signal and lighting cables added on top.
  • Side drains and culvert extensions – a drain trench runs parallel to the road for kilometres, exactly where cables tend to be laid.
  • Flyover, underpass and foot-over-bridge foundations – piles need a clear footprint, and diverting a service late is costly.
  • Ducts and crossings under the carriageway – HDD or push crossings that must keep clear of existing lines.
  • Municipal road reconstruction – urban roads in NCR and other cities, where record drawings rarely match the ground.

A highway GPR survey and a city-street survey use the same radar, EM locating and ground marking. What differs is the width of corridor scanned and the traffic arrangement around the crew.

How is a road corridor survey priced on our rate card?

Road work is billed per metre surveyed: ₹24 for a standard survey, and ₹32 when an L-section depth profile is ordered. The minimum order is ₹50,000 in Delhi NCR (up to 2 km) and ₹1,00,000 in the rest of India (up to 4 km). Inside Delhi NCR the minimum order is ₹50,000; elsewhere a project is billed at no less than ₹1,00,000. GST is added on top.

Road jobBillingBefore GST
2 km junction improvement, Faridabad₹48,000, minimum order applies₹50,000
2 km junction improvement outside NCR₹1,00,000 minimum order applies₹1,00,000
6 km sector road, Gurugram6 km at ₹24/m₹1,44,000
120 km highway with L-section₹32/m less 25% = ₹24/m₹28,80,000

Long road orders cross the slabs – 25%, 40% and 50% off above 100, 500 and 1,000 km – and the cut applies to every metre. Lane closures and other traffic arrangements, night shifts, mobilisation and CAD/GIS drawing sets always appear as separate lines. The full table is on our GPR survey price list.

Road corridors across the capital region are covered from our Faridabad base – see GPR survey in Delhi NCR – and state-wide work in Gujarat is set out on GPR survey in Gujarat.

TIP 1

Define the corridor band

Give the acquisition boundary, not just the road edge, so shoulders and widening land are scanned along with the carriageway.

TIP 2

List every structure

Culverts, bridges, junctions and rail overbridges each need closer scan lines, so mark their chainages on the drawing you send.

TIP 3

Plan traffic arrangements

Cones, tapers and marshals come under the project's permission and are billed separately; agree who supplies them before mobilisation.

TIP 4

Allow for night shifts

High-volume sections may only be workable at night, and night working is a separate item, so budget for it at the start.

TIP 5

Nominate critical crossings

Where a strike would halt the works, ask for a trial pit at that crossing to confirm what the radar found.

Insights

Road and highway GPR survey in numbers

Rate per metre by order size

Standard vs L-section GPR survey, ₹ per metre

StandardL-Section
₹0₹20₹40₹60₹80₹24₹32Up to 100 km₹18₹24100+ km₹14.4₹19.2500+ km₹12₹161,000+ km

Source: Mezux rate card, October 2026.

Standard survey cost for typical orders

Standard ₹24/m, ₹ lakh before GST, slab applied

₹0 L₹30 L₹60 L₹90 L₹120 L₹2.4 L10 km₹12 L50 km₹27 L150 km₹86.4 L600 km

Source: Mezux rate card – amounts before GST.

Our recorded output

Route surveyed, km

0 km300 km600 km900 km1200 km100 kmPeak day700 kmFastest 30 days

Source: Mezux delivery records.

Fact table

FactValueSource
Standard road survey rate₹24 per metreMezux rate card
L-section survey rate₹32 per metreMezux rate card
Minimum order₹50,000 in Delhi NCR (up to 2 km); ₹1,00,000 elsewhere (up to 4 km)Mezux rate card
Peak output on open corridors100 km in a dayMezux records

Traffic arrangements, night shifts, mobilisation and drawing sets are charged separately; GST is extra.

Best prices

Get GPR Road and Highway Survey at Best Prices

Flat rate for any road

Municipal street or national highway, the standard survey is ₹24 per metre, so road packages of any class compare easily.

NCR jobs: ₹50,000 minimum

Inside Delhi NCR a short road job is charged the ₹50,000 minimum order, not ₹1,00,000.

L-section for deep crossings

Pay ₹32 per metre only on stretches where drains, ducts or bores need the depth profile, and keep the rest standard.

Slab discount on long roads

Orders above 100 km cost 25% less per metre, above 500 km 40% less, and above 1,000 km half as much.

No rental mark-up

Every radar sent to your road belongs to Mezux and the crew is our own, so no hire or sub-letting margin applies.

Traffic items listed apart

Lane closures, marshalling, night shifts and drawings are separate lines, so the survey rate itself stays easy to check.

Latest price list

Road and Highway GPR Survey Rates – Current Rates

ServiceUp to 100 kmAbove 100 km
(25% off)
Above 500 km
(40% off)
Above 1,000 km
(50% off)
Standard GPR Survey
min. order ₹50,000 NCR · ₹1,00,000 India
₹24/m₹18/m₹14.40/m₹12/m
L-Section GPR Survey
min. order ₹50,000 NCR · ₹1,00,000 India
₹32/m₹24/m₹19.20/m₹16/m

Rates per running metre of route surveyed. GST extra. Discount applies to the whole order quantity once it crosses the slab. Outside Delhi NCR the minimum order is ₹1,00,000 (covers up to 4 km). Mobilisation, night working, traffic and permission arrangements and drawing sets (CAD/GIS) are listed separately in the quote. Updated 23 October 2026.

Price range

Lowest rate₹12/mStandard, above 1,000 km
Highest rate₹32/mL-Section, up to 100 km
Minimum order₹50,000Delhi NCR (up to 2 km) · ₹1,00,000 Rest of India (up to 4 km)
FAQ

More questions on road and highway utility surveys

Do you mark findings on the road surface as well?

Yes. Each detected service is marked on the carriageway or verge in paint, or with pegs on soft ground, with its approximate depth noted beside the mark. Marks wear quickly under traffic and rain, so they guide excavation that follows soon after; the signed report and crossing schedule keep the permanent record.

How close together are the scan lines on a road survey?

Lines run along the corridor with cross-lines at regular gaps and at every chamber, pole, marker stone and junction. Spacing is tightened where services converge, such as at culverts and intersections. The exact spacing for your package is set in the scan plan before mobilisation, because it decides how small a service the survey can reliably pick up.

Can GPR tell a water main from a power cable?

Not always from radar alone. Radar shows that something is there and roughly how deep; EM tracing can confirm a live cable or a metal pipe, and chambers, markers or surface fittings often settle the rest. Where the type still cannot be confirmed, the line is reported as unidentified so nobody digs near it with false confidence.

What happens if a service sits exactly where a pile or drain is designed?

The conflict is reported with its chainage, offset and approximate depth, so the designer can move the element, plan protection or start a shifting request with the service owner. Where the exact depth or identity matters to that decision, a trial pit at the point can be ordered as a separate item.

Is the survey useful for municipal roads, not only highways?

Yes, and city streets usually need it more. Municipal roads carry house connections, street-lighting cables, storm drains and several operators' ducts within a narrow width. The method and the ₹24 per metre rate are the same; scan lines are closer and working hours are often shorter because of traffic and frontage access.

How soon can a crew start on a road package?

Because the GPR systems are our own, the start date depends on crew planning, travel from Faridabad and your permissions rather than on hiring equipment. Road permissions and traffic arrangements often take the longest, so starting them early helps. The quote includes a programme, and the start date is confirmed in writing when the order is placed.

What width do you survey on a road corridor?

The full corridor including shoulder, median and acquisition land — that is where most findings are, not under the carriageway.

Is the crossing schedule really the main output?

Yes. It is what a site engineer works from. CAD or GIS files, if ordered separately, support it rather than replacing it.

Can you assess pavement in the same visit?

Where specified, yes — bound course thickness and sub-base condition come from the same radar pass.

Do you work on live carriageways?

Regularly, under a traffic management plan, with night working normal on high-volume sections.

Will you help write our tender scope?

Yes, even where we end up not bidding. A loose scope invites offers that price different things.

Get a quote

Send your road chainage and scope

What to send for an exact quote

  • Route drawing, KML or list of roads with start and end points
  • City / district and site type (road, estate, plant)
  • Standard survey or L-section
  • Target start date and any working-hour limits
Standard GPR₹24/m
L-Section GPR₹32/m

₹24/m · Min. order ₹50,000 — Delhi NCR (up to 2 km) · Min. order ₹1,00,000 — Rest of India (up to 4 km) · GST extra · 25–50% off above 100 km.

What happens next

  1. Scope check – we confirm route length, crossings and L-section need.
  2. Written quote – rate, slab, minimums, extras and a day-by-day programme.
  3. Mobilisation – our own crew and systems on the agreed date.

Get a Quote

Route length, location and survey type – we reply with a written quote.

Trusted by India’s telecom & infrastructure leaders

Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks
Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks