Sector · GPR Survey
GPR Survey for Metro Rail & Railway Infrastructure Projects
Work measured in possession hours rather than working days — where the survey has to be finished before the first train of the morning.
Since 2003 we have surveyed over 1.5 lakh km by radar, held 100 km a day at peak and delivered 700 KM inside 30 days without hiring a single system. Outside Delhi NCR we accept projects from ₹1,00,000 upward, since rigs and crews travel from our Faridabad base. Within NCR the minimum order is ₹50,000 (covers up to 2 km).
Quick AnswerMezux Touch surveys metro and railway corridors for project authorities, general consultants and civil packages. Work covers alignment utility clearance ahead of design freeze, track formation and ballast condition, station box and depot areas, and third-party crossings of operational railway land.
The programme is written by the possession, not by us
On operational railway and metro land, work happens inside a possession — a defined block, often a few hours at night, granted months in advance and immovable. Everything about the survey plans backwards from that window.
Setout, calibration, equipment checks and crew briefing all complete before the block opens, because a possession spent preparing is a possession wasted and the next one may be weeks away. Data review happens the same night so that if a re-scan is needed we know before the block closes rather than after.
This is the discipline that separates rail-competent survey teams from general ones, and it is why we programme rail work separately from ordinary corridor work, with night-shift working listed as its own item beside the standard metre rate.
Alignment clearance before design freeze
A metro alignment designed over an unmapped trunk sewer or HT feeder becomes a diversion, and a diversion has its own approval timeline with the asset owner that runs independently of the construction programme.
Establishing what is buried before design freeze is therefore the cheapest possible point to spend this money. It lets the design team route around what can be avoided, and lets the diversion applications for what cannot be avoided start months before the site does.
Deliverables follow the SUE framework so the project's design risk register records what was detected, what was verified physically and what remains an assumption.
Track formation and ballast
Beyond utilities, radar reads the track structure itself — ballast depth and fouling, the formation interface, and the ballast pockets and wet beds that indicate loss of support beneath sleepers.
This is condition assessment rather than utility detection, and it answers a different question: not what is buried, but whether the structure supporting the track is doing its job. On maintenance planning it lets renewal be targeted at the sections that need it rather than applied by route length.
Station boxes, depots and third-party crossings
Station box excavation and depot construction need the plot cleared before piling, and both usually sit in built-up areas where the surrounding servicing is dense and poorly recorded.
Third-party crossings of railway land — a utility or fibre route passing under the track — are a separate discipline again, with cover requirements set by the railway rather than by the client, and an approval route that runs on its own timeline. Our liaison desk handles those files.
Depots, viaducts and the wider package
Alignment work is only part of a metro package. Depot construction covers a large plot that has to be cleared before piling; viaduct pier locations each need their own clearance; and cut-and-cover sections behave like deep urban excavation with all the servicing that implies.
Each of these has a different survey geometry and a different confidence requirement, and treating them as one undifferentiated scope is how a package ends up under-surveyed at exactly the points that matter.
Coverage spans 28+ States/UTs on 58 owned systems. See void detection and SUE survey.
Working with the general consultant
On most metro packages the survey answers to a general consultant rather than directly to the authority, and the deliverable has to satisfy their design assurance process rather than just the site team.
That means the SUE quality level is stated per element, the residual risk register is written so it can be adopted into the project register directly, and every drawing is issued under document control so a superseded revision cannot stay in circulation.
We prepare packs knowing a design assurance reviewer will read them, which changes how limitations and confidence are worded compared with a contractor-facing drawing.
Third-party crossings of operational land
Utilities and fibre routes crossing under operational track are their own category. Cover requirement is set by the railway, the bore profile must satisfy their structural review, and the approval runs on a timeline driven by possessions rather than by the applicant.
We survey, design the crossing profile and carry the approval file through our own liaison desk, so the technical case and the permission move together rather than sequentially.
These are planned months ahead. A crossing identified late is the item that holds an otherwise complete corridor.
FAQ
Metro Rail & Railways — common questions
Yes, and we programme rail work around it. Setout, calibration and briefing complete before the block opens, and data is reviewed the same night so a re-scan is identified before the block closes.
Because a diversion discovered at construction stage has an approval timeline with the asset owner that runs independently of your programme. Before freeze, the design can route around it instead.
Yes — ballast depth, fouling, the formation interface and wet beds indicating loss of support. That is condition assessment rather than utility detection, and it lets renewal be targeted rather than applied by route length.
Yes, including the approval file. Cover requirements are set by the railway rather than the client, and the approval runs on possession-driven timelines that need starting months ahead.
Field detection throughout as the working basis, with physical verification at crossings where a pile cap, box or deep structure cannot tolerate uncertainty. We help set this per element rather than blanket-specifying.
Outside Delhi NCR the minimum accepted GPR order value is Rs 1,00,000 per project, because mobilisation runs from Faridabad. Metro and railway packages are well above this threshold in practice. Within Delhi NCR the minimum order is ₹50,000 (covers up to 2 km).
Our fastest recorded delivery is 700 kilometres in 30 days on our own fleet. On possession-constrained corridors the limit is block availability rather than crew capacity, and we plan against that.
Running night shifts on our own fleet, we can reach roughly 100 km a day where a corridor is open. Our strongest month: 700 KM in 30 days. Company-wide, radar coverage has passed 1.5 lakh km. Speed on a metro alignment is governed by ground congestion and by what the report needs to prove.
Have an alignment approaching design freeze?
Send the corridor and your possession calendar — we will build the survey programme around the blocks you actually have.
Request a Sector QuoteGPR for metro and railway projects — specifications, standards and detailed questions
Mezux Touch programmes rail work around possessions rather than around working days, and that single constraint shapes everything else. A possession is a defined block, often a few hours at night, granted months in advance and immovable. Setout, calibration, equipment checks and crew briefing all complete before the block opens, because a possession spent preparing is a possession wasted and the next may be weeks away. Data is reviewed the same night, so that if a re-scan is needed we know before the block closes rather than after.
How the work is run
Alignment clearance is done before design freeze rather than before construction, because a diversion discovered at construction stage has an approval timeline with the asset owner that runs independently of the project programme. SUE quality level is stated per element rather than blanket-specified, so a station box or pile cap gets verification while a general corridor does not. For track condition work the method differs entirely: continuous ballast depth and formation profiling rather than utility detection. Packs are prepared knowing a design assurance reviewer will read them alongside a site engineer.
What you receive
A signed survey report and a residual risk register written for direct adoption into the project register; alignment utility drawings stating the SUE quality level per element are available as a separately quoted CAD/GIS drawing set. Ballast depth, fouling and formation interface profiles as a separate condition assessment where track work is in scope, with wet beds and loss of support identified. Station box and depot plot clearance issued as area surveys rather than corridor drawings. Third-party crossing packs formatted for the railway's own structural review, since cover requirements are set by them rather than by the client. All issued under document control so a superseded revision cannot remain in circulation.
Beyond the basics
Can you work inside a night possession? Yes, and rail work is programmed around it. Setout and calibration complete before the block opens, and data is reviewed the same night.
Why survey before design freeze rather than construction? Because a diversion found at construction stage has an approval timeline with the asset owner that runs independently of your programme.
Can radar assess ballast condition? Yes — depth, fouling, the formation interface and wet beds indicating loss of support. That is condition assessment rather than utility detection.
What SUE level should a metro alignment specify? Field detection throughout as the working basis, with verification at crossings where a pile cap or box cannot tolerate uncertainty. We help set it per element.
Who sets the cover on a crossing of railway land? The railway, not the client, and the approval runs on possession-driven timelines that need starting months ahead.
Terms used on this page
Possession — a defined block of time during which work on an operational alignment is permitted. Ballast fouling — contamination of track ballast by fines, which impairs drainage and support. Wet bed — a saturated zone beneath sleepers indicating loss of support, detectable by radar. Formation interface — the boundary between ballast and the prepared subgrade beneath it. Design freeze — the point after which alignment changes become expensive, and therefore the deadline for utility clearance.
Underground utility detection for metro projects means locating the cables, pipes, ducts and sewers along an alignment, at station sites and at pier positions before design is fixed. Mezux Touch does it with 58 owned GPR systems and EM locators at ₹24 per metre (₹32 with L-section), with a minimum order of ₹50,000 in NCR and ₹1,00,000 elsewhere; GST and night work are extra.
Rates and page checked:

- STEP 1Alignment and elements listed
- STEP 2Radar and EM passes
- STEP 3Services marked on site
- STEP 4Report with confidence stated
What should underground utility detection for metro projects answer?
Underground utility detection for metro projects is only useful if it answers the questions the design and construction teams will actually ask. On metro and railway packages those questions usually fall into a short list:
- What runs under each pier, column or foundation footprint? One unknown cable or water main beneath a pile position means a redesign or a diversion.
- Which services cross the alignment, and how deep are they? Trunk water mains, sewers, HT cables, gas lines and telecom ducts each need a decision: protect, divert or avoid.
- What lies under the footpaths at station entries? Lifts, stairways and ventilation shafts are often placed in the most crowded strip of the street.
- Which lines are missing from the records? Plastic water pipes and abandoned cables rarely appear on old drawings, and radar is the method that picks up non-metallic lines.
- Where does the survey stop being reliable? Radar reach depends on soil and moisture, so a deep sewer or wet clay can put some services beyond it, and the report says so section by section.
We combine 2D radar lines with EM locating for conductive services, and switch to 3D or high-resolution GPR on congested patches such as junctions and station sites. Where a depth must be proved before design, trial pits or boreholes are added on request.
Which GPR services and city pages suit metro and railway teams?
Different stages of a metro or railway package draw on different survey scopes. These pages explain each one in detail:
- SUE survey – utility information graded by quality level, for consultants who need confidence stated per feature.
- Pre-excavation utility scanning – clearance of pile, pier and trench positions shortly before the civil crew digs.
- HDD route survey – bore-path scanning where a diverted service or a new cable has to pass under the track or a road.
- CAD/GIS utility mapping – findings issued as drawing sets or GIS layers for the design model, quoted as a separate item.
For local ground, crossings and pricing, our city pages cover places where metro or suburban rail work is under way, such as Delhi NCR, Ahmedabad and Mumbai. Crews for every city travel from our Faridabad base with company-owned systems, and survey work is never sub-let.
How is a metro or railway GPR survey priced?
Metro work is billed on the same published card as any other route: ₹24 per metre for a standard GPR survey, or ₹32 per metre where an L-section depth profile of detected services is wanted along the alignment. The minimum order is ₹50,000 in Delhi NCR (up to 2 km) and ₹1,00,000 in the rest of India (up to 4 km). Outside Delhi NCR a project is never billed below ₹1,00,000; inside NCR the minimum order is ₹50,000. GST is added on top.
Long packages gain from the whole-order slabs, which cover every metre once the total crosses them: 25% off above 100 km, 40% above 500 km and 50% above 1,000 km.
| Example scope | Working | Before GST |
|---|---|---|
| 18 km elevated corridor, standard | 18,000 m × ₹24 | ₹4,32,000 |
| Same corridor, L-section on 5 km of crossings | 5,000 m × ₹32 + 13,000 m × ₹24 | ₹4,72,000 |
| 220 km multi-line programme, standard | 2,20,000 m × ₹24, less 25% | ₹39,60,000 |
Station boxes and depot plots are scanned on a grid, and the quote converts that grid into scan-line metres at the same rate. Because rail work leans heavily on night possessions, remember that night-shift working sits outside the metre rate, along with mobilisation, traffic arrangements or permissions and CAD/GIS drawing sets; each appears as its own line in the quote. The full card, with worked examples, is on our GPR survey price list.
Guides for metro and railway utility work
Metro and railway GPR survey in numbers
Rate per metre by order size
Standard vs L-section GPR survey, ₹ per metre
Source: Mezux rate card, October 2026.
What a short route costs
Standard ₹24/m, ₹ lakh before GST
Source: Mezux rate card – amounts before GST.
Our recorded output
Route surveyed, km
Source: Mezux delivery records.
Fact table
| Fact | Value | Source |
|---|---|---|
| Standard GPR survey | ₹24 per metre | Mezux rate card |
| L-section GPR survey | ₹32 per metre | Mezux rate card |
| Minimum order | ₹50,000 per order (covers up to 2 km) | Mezux rate card |
| Project minimum outside Delhi NCR | ₹1,00,000 | Mezux rate card |
| Peak survey output | 100 km a day on open corridors | Mezux records |
| Company-owned GPR systems | 58 | Mezux records |
Night-shift working, mobilisation, traffic arrangements and CAD/GIS drawing sets are charged separately from the metre rate; GST is extra.
Get GPR Survey for Metro Rail Projects at Best Prices
Published metre rate
Metro corridors are billed at ₹24 per metre for a standard survey, the same card that applies to every other kind of route.
Profile only key stretches
Order the ₹32 L-section just for crossings and congested lengths, and keep open viaduct stretches at the standard rate.
Slabs on long packages
A multi-line programme past 100 km gets 25% off every metre, rising to 40% beyond 500 km and 50% beyond 1,000 km.
No hired radar
Fifty-eight company-owned GPR systems and in-house crews mean the price carries no equipment-hire cost and no sub-contractor margin.
Night work shown clearly
Possession and night-shift working is quoted as its own item, so the authority sees exactly what the block programme adds.
Drawings only when ordered
CAD drawing sets and GIS layers are priced separately, so they are paid for only when the design consultant actually needs them.
GPR Survey Rates for Metro and Railway Projects – Current Rates
| Service | Up to 100 km | Above 100 km (25% off) | Above 500 km (40% off) | Above 1,000 km (50% off) |
|---|---|---|---|---|
| Standard GPR Survey min. order ₹50,000 NCR · ₹1,00,000 India | ₹24/m | ₹18/m | ₹14.40/m | ₹12/m |
| L-Section GPR Survey min. order ₹50,000 NCR · ₹1,00,000 India | ₹32/m | ₹24/m | ₹19.20/m | ₹16/m |
Per-metre rates, GST added on the invoice. The slab discount covers the full order quantity, not only the part above the slab. A ₹1,00,000 per-project minimum applies outside Delhi NCR. Separate from the per-metre rate: mobilisation, night shifts, traffic or permission arrangements and CAD/GIS drawings. Updated 23 October 2026.
Price range
More questions about GPR survey for metro and railway work
Can radar pick up plastic water mains along a metro alignment?
Yes, in most ground. EM locators follow only conductive lines, so HDPE, PVC and other non-metallic pipes are found with radar, which responds to the contrast between pipe and soil. Small plastic pipes in wet clay are the hardest case, and the report gives such finds a lower confidence where that applies.
Do pier positions on an elevated corridor need more than a strip scan?
Usually, yes. A strip along the centre line shows what runs along and across the route, but each pier footprint benefits from a closer grid covering the pile group and its working space, so any diversion can be planned before piling. The pier list and grid size are agreed with you at quotation stage.
Is work inside a night possession charged at the normal rate?
The survey itself is charged at the normal metre rate. Night-shift working is billed as a separate item, as are mobilisation, traffic arrangements or permissions and any CAD/GIS drawing sets. The quote lists each one, so the project team can see exactly what the night programme adds to the cost.
Can the survey cover lift and stairway positions at station entries?
Yes. Entry structures usually sit on footpaths or in the outer lane, where water connections, street-light cables, telecom ducts and drains crowd together. Each proposed footprint is scanned on a tight grid with radar and EM, every find is marked on the surface with approximate depth, and the structure can then be shifted or services diverted early.
Do you work alongside the civil contractor's own trial-pit team?
Yes. Many packages already have an excavation team on site. We can nominate the points where a pit would settle a depth or identity question, attend while it is opened and record the result against the survey. If you prefer, we can also arrange trial pits or boreholes ourselves on request.
Will radar see a deep trunk sewer under a city road?
That depends on the ground and on how deep the sewer is. Wet clay and saline soil cut radar reach, while dry sandy ground helps it. If a sewer lies below the reach achieved on that section, the report says so rather than guessing, and a borehole or pit can confirm its level where the design depends on it.
GPR survey in metro and rail cities
- GPR survey in Delhi
- Mumbai GPR survey
- GPR survey company in Bengaluru
- Underground utility survey in Chennai
- Ground penetrating radar survey in Hyderabad
- Cable and pipe detection in Kolkata
- GPR survey in Pune
- Ahmedabad GPR survey
- GPR survey company in Gurugram
- Underground utility survey in Noida
- Ground penetrating radar survey in Jaipur
- Cable and pipe detection in Lucknow
- GPR survey in Indore
- Bhopal GPR survey
- GPR survey company in Patna
- Underground utility survey in Chandigarh
- Ground penetrating radar survey in Nagpur
- Cable and pipe detection in Kochi
- GPR survey in Guwahati
- Bhubaneswar GPR survey
Survey services used on rail packages
- HT/LT underground cable mapping
- Expressway utility survey
- Utility survey before HDD
- GPR mapping for electrical utilities
- GPR profiling (L-section)
- Corridor utility survey
- GIS & CAD utility mapping
- GPR scanning along routes and sites
- GPR survey cost guide
- Construction site GPR survey
- Telecom duct route feasibility survey
- Road widening utility survey
- GPR survey for city gas networks
- Road void detection
- Telecom route survey
- Pre-excavation utility scanning
- Turnkey utility survey for EPC
- Buried utility mapping
- Water and sewer line survey
- Sectors we survey for
Send your metro or railway alignment
What to send for an exact quote
- Route drawing, KML or list of roads with start and end points
- City / district and site type (road, estate, plant)
- Standard survey or L-section
- Target start date and any working-hour limits
₹24/m · Min. order ₹50,000 — Delhi NCR (up to 2 km) · Min. order ₹1,00,000 — Rest of India (up to 4 km) · GST extra · 25–50% off above 100 km.
What happens next
- Scope check – we confirm route length, crossings and L-section need.
- Written quote – rate, slab, minimums, extras and a day-by-day programme.
- Mobilisation – our own crew and systems on the agreed date.
Popular searches — metro and railway utility clearance
Related searches
SUE level per element|possession working|ballast and formation survey|alignment crossing approval
GPR survey by city
GPR survey Pune|GPR survey Jaipur|GPR survey Nagpur|GPR survey Visakhapatnam
By sector
pipeline leak detection survey|HT cable locating for utilities|concrete scanning and rebar detection






