Survey, permission and bore delivered as one programme — because on a fibre rollout the thing that slips is never the drilling.

Quick AnswerWe deliver telecom underground infrastructure end to end: route survey, RoW permissions, HDD crossings, duct installation, fibre blowing and splicing. Scheduling those against one another under a single contract is what keeps a rollout on programme.

What our telecom record actually consists of

Three corridors carry most of what a prospective operator would want to test: 135 KM at Bawana, 225 KM for NDMC and 67 KM at Okhla, each completed under multi-authority compliance and, in two cases, materially below approved capex.

They are named with clients and dates rather than described as capability, which means they can be asked about specifically. We would rather be asked what went wrong on them than what went right, because a corridor of that length with no difficult stretches is a corridor somebody is not describing fully.

Beyond those, we are a registered service partner to leading national operators and work both directly and as a specialist subcontractor within EPC packages.

Working directly against working within a package

A direct engagement lets us schedule survey, permissions and drilling against one another rather than sequentially, which is where most of the time on a rollout is recovered.

Inside an EPC package our scope is narrower and the sequence belongs to someone else, so we say plainly what that changes: we can commit to our own crews and plant, but not to a programme we do not control.

Which arrangement suits a client depends on how their own contracting is structured, and we are happy to work either way provided the boundary is stated rather than assumed.

The part of a rollout clients underestimate

Not the drilling and not the cable. The consent workload — hundreds of small approvals from societies, facility managers, ward offices and estate managers, none of which appear on a network design and none of which a construction schedule accounts for.

We carry that as a tracked workload with named accountability per cluster or corridor rather than as an operational detail, because it is the single most common reason a technically complete rollout has not energised.

Clients who budget for construction and treat approvals as administration are the ones whose programmes report ninety per cent complete for several months.

How we are usually engaged

Directly by operators on their own projects, and as a specialist subcontractor inside EPC packages where the main contractor holds the sequence.

The two are different commitments and we state which applies. Directly, we can commit to a programme because we control the order of work. Inside a package we commit to our own crews, plant and quality but not to a date that depends on others.

That distinction is worth making at tender rather than after award, because a client who believes they have a programme commitment and has not is the one who is disappointed later.

Delivered corridors

135 KM at Bawana, 225 KM for NDMC and 67 KM at Okhla, each completed under multi-authority compliance. We are a registered service partner to leading national operators.

Capacity behind that is 14 owned radar systems and 18 owned HDD rigs, with peak survey output reaching 100 km a day.

Frequently asked questions

Yes, and it is how most of our telecom work runs. Scheduling the three against one another is what lets a crew mobilise the week a sanction lands rather than the week after.

Yes. Layer naming and file format are agreed in writing before drafting, with detection method and confidence carried as attributes on every feature.

Usually problems created at duct stage — duct condition, joint quality and route setout. They surface weeks later as a blow that will not complete.

Yes, rather than reporting a pass. The trace is the only honest record of the loss budget the network will actually operate on.

Regularly, and it is the request we get most from clients who have already had an outage that should have been impossible on paper.

Have a circle rollout with a fixed go-live?

Send the route schedule and target dates — we will work backwards from permissions and say what is deliverable.

Get A Quote +91 99100 10209

Engaging us on telecom work — models, boundaries and detailed questions

There are two ways operators and contractors use us on telecom projects, and they carry different commitments. A direct award lets us sequence survey, permissions and construction against one another, which is where most of the recoverable time on a rollout sits. Inside an EPC package our scope is narrower and the sequence belongs to someone else.

What changes between the two

Under a direct award we commit to a programme, because we control the order in which crossings, permissions and construction happen. Inside a package we commit to our own crews, plant and quality, and to a start date once the preceding work is complete — but not to an end date that depends on parties we do not direct. Stating that boundary at tender rather than after award is the difference between a working relationship and a dispute, and it is a distinction a surprising number of contractors leave vague.

What we bring under either model

Fourteen owned GPR systems, eighteen owned HDD rigs and directly employed crews, so a mobilisation date does not depend on a hire yard under either arrangement. An in-house permission desk, which matters more inside a package than outside it because it removes one dependency from an already dependent position. And a delivered record that can be checked: 135 KM at Bawana, 225 KM for NDMC, 67 KM at Okhla, each with a client and a date attached.

Beyond the basics

Do you prefer direct awards? For corridor work, yes, because we can only commit to a programme we sequence. For specialist scope inside a package we are content either way provided the boundary is written down.

What will you not commit to inside an EPC package? An end date that depends on preceding work by others. We commit to our own crews, plant, quality and a start date once the handover is ready.

Are you empanelled with operators? Yes, as a registered service partner to leading national operators, which is a commercial vetting rather than a statement about any specific corridor.

Can we check the delivered record? Ask about Bawana, NDMC or Okhla specifically, including what did not go to plan. That answer is more informative than the delivery figures.

Does the model change your rates? Not materially. It changes what we can promise about programme, which is worth more to most clients than a rate difference.

Terms used on this page

Direct award — a contract from the operator or ISP itself, where we hold the sequence. EPC package — work inside another contractor scope, where the sequence sits elsewhere. Empanelment — commercial and technical vetting by an operator, distinct from project performance. Sequence control — authority over the order of work, which is what makes a programme commitment possible. Dependency — a task whose start depends on another party completing theirs.

Trusted by India’s telecom & infrastructure leaders

Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks
Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks