Skip to main content
ISO 9001:2015 · ISO 14001:2015 · ISO 45001:2018

GPR Services

Construction Site GPR Survey and Pre-Excavation Clearance

The cheapest day to find a buried foundation is the day before you excavate. The most expensive is the day the piling rig meets it.

What a cleared site still contains

A demolished building leaves footings.A cleared plot leaves a septic tank.A levelled field leaves a well.The surface tells you none of it.

Site clearance removes what is above ground. Everything below stays exactly where it was, and on a plot with any history that is usually more than the developer has been told about.

Buried structures · Chambers and tanks · Abandoned borewells · Live services

Quick AnswerMezux Touch carries out pre-construction GPR survey for site clearance — detecting buried foundations, chambers, septic tanks, abandoned borewells and live services before excavation begins, so a piling programme is set out against measured ground rather than a demolition assumption.

Timing is the whole value of this survey

Found before excavation, a buried footing is a setting-out adjustment. Found by a piling rig, it is a stopped programme, a damaged tool and a redesign under time pressure.

That is why we push clients to survey after demolition and before setting out rather than at either end. A survey commissioned once piling has started is investigating a problem instead of preventing one.

What we find that clients did not expect

Old footings and basement slabs from demolished structures are the most common. After that: septic tanks and soak pits, disused chambers, abandoned borewells, and on former agricultural land, brick-lined wells and irrigation channels beneath levelling fill.

A vertical void beneath a proposed footing is a different order of problem from a service line, so we report structural findings in their own schedule rather than mixing them into a utility drawing.

Site clearance sequence

How a site survey runs

What was on this plot before?

Demolition drawings, old imagery and local knowledge tell us what to look for. A plot that held a factory and one that held houses leave entirely different things behind.

Area coverage rather than a corridor

Site work is surveyed as an area on a grid rather than as a route, with spacing set against the smallest feature that would affect the foundation design.

Footings, slabs and basements

Buried structural remains are mapped with their outline rather than as a point, because the design question is how much of the footprint is affected.

Tanks, soak pits and borewells

Vertical voids and buried chambers are reported in their own schedule, since a cavity beneath a proposed footing is a structural matter rather than a utility clash.

Live connections still in the ground

Incoming services frequently remain live after demolition. These are identified and reported as live or unverified rather than assumed disconnected.

Stating what the ground allowed

Achievable depth is stated for the site rather than assumed, because made ground and demolition rubble both limit how far radar usefully reaches.

Findings against your setting-out

Where the client provides the proposed foundation layout, results can be overlaid on it as a drawing set, quoted separately from the survey rate, so clashes are visible rather than requiring interpretation.

What is worth verifying before piling

Where a finding sits under a critical foundation element, we nominate it for trial excavation rather than leaving the design team to decide on a radar image alone.

Greenfield sites are not empty either

Land that was agricultural within living memory carries field drains, irrigation channels, open wells and abandoned borewells beneath the levelling fill. None of it appears on a developer's layout.

A brick-lined well beneath a proposed footing is a structural problem discovered late, and it is entirely findable early.

NCR development areas we clear

Underground chamber detection is part of every site clearance here, since disused inspection chambers and soak pits survive demolition almost without exception. A GPR survey for construction is commissioned for one reason above all others: underground structure detection before setting out, so a piling programme is not designed against an assumption about what demolition left behind. Plots across the capital region are surveyed before setting out. What a site is likely to contain depends heavily on which area it sits in:

GPR survey in Rohini|GPR survey in Dwarka|GPR survey in Saket|GPR survey in Gurugram|GPR survey in Noida|GPR survey in Faridabad|GPR survey in Ghaziabad|GPR survey in Greater Noida

About to set out a piling programme?

Survey after demolition and before setting out — that week is when this costs least and prevents most.

Get A Quote +91 99100 10209

Construction site survey — timing, findings and detailed questions

Site clearance surveys are commissioned at three points and only one of them is right. Before demolition misses what demolition exposes. After piling begins is investigation rather than prevention. Between the two, when the plot is clear and setting out has not started, is when the same survey costs least and changes most.

Why structural findings are reported separately

A buried footing, a septic tank and an abandoned borewell are structural matters for the foundation designer. A live cable is a safety matter for the excavation contractor. Presenting both on one drawing means whichever reader is looking has to filter out half of it, and on a busy site the filtering does not happen. We issue two schedules for that reason, and the structural one usually reaches the design team while the services one reaches the site.

What is delivered

A site plan showing detected features with outlines rather than points, so the affected footprint is visible. A structural findings schedule covering buried footings, slabs, chambers, tanks and vertical voids. A services schedule with confidence per feature and live or unverified status stated. Achievable depth for that specific site given the made ground present. Where the foundation layout is supplied, an overlay showing clashes directly can be prepared as a separately quoted drawing set. Recommendations for trial excavation where a finding sits beneath a critical element.

Beyond the basics

Can you find a septic tank reliably? Usually, since a buried chamber returns strongly. Depth and surrounding material affect it, and we state confidence per feature.

What about deep basements from old structures? Detectable to the depth the ground allows. Where a basement is deeper than radar reaches, we say so rather than implying full clearance.

Is a greenfield site worth surveying? Yes, if it was agricultural. Field drains, wells and borewells beneath levelling fill are common and none appear on a layout.

Who uses the structural schedule? The foundation designer, usually before setting out. The services schedule goes to the excavation contractor, which is why they are separate.

Do you attend during piling? On request, for spot clearance ahead of the rig. It is more expensive than surveying the whole site beforehand and occasionally worth it.

Terms used on this page

Setting out — marking the foundation layout on site, the point after which changes cost more. Vertical void — an abandoned borewell, well or shaft, a structural hazard rather than a utility. Made ground — material placed by people, including demolition rubble, which limits survey depth. Overlay — survey findings plotted against a proposed layout so clashes are directly visible. Trial excavation — exposing a detected feature to confirm it before a design decision depends on it.

Construction Site GPR Survey
Quick answer

A construction site GPR survey scans a cleared plot on a grid to find old footings, slabs, tanks, abandoned borewells and live service lines before setting out. Mezux Touch charges ₹24 per metre of scan line, with a minimum order of ₹50,000 in Delhi NCR and ₹1,00,000 elsewhere, and GST extra; mobilisation and drawing sets are quoted separately.

Rates and page checked:

Survey team pushing a radar cart across an open, levelled construction plot
Grid lines on a cleared plot are run before any pile position is pegged.
Workers hand-digging a shallow trial trench to expose a buried line
A short hand-dug trench confirms a finding that sits under a critical footing.
Checklist of plot details collected before a site radar survey begins
Demolition history, layout and access times shape the grid for each plot.
Printed survey report with a findings schedule and site sketch
Structural and service findings are issued as separate schedules to different readers.
How it works · Clearing a plot before piling
HT cableWater mainOFC ductGas lineRADARGRAM
  1. STEP 1Plot history collected
  2. STEP 2Grid scanned by radar
  3. STEP 3Structures and services separated
  4. STEP 4Findings issued before setting out

When does a construction site need a GPR survey?

A construction site GPR survey earns its cost whenever the ground under a plot has a past that nobody fully recorded. The common triggers are:

  • Redevelopment after demolition – a house, factory or warehouse came down, and its footings, tanks and connections may still be below grade.
  • Piling or raft foundations – a rig meeting an old slab or a brick-lined well stops the programme, so the pile grid needs clearing first.
  • Basement excavation beside a road, where live water, power and telecom lines run close to the boundary.
  • New incoming services – power, water, sewer and fibre connections cut from the plot edge to the public network.
  • Former farmland turned into a layout, where field drains and wells lie under levelling fill.

The same approach works as a ground radar survey for infrastructure projects such as substations, pumping stations, depots and treatment plants, where foundations and buried services share a compact footprint. If the plot is clean, the survey says so in writing; if it is not, the design team learns early enough to move a pile or a footing at no real cost.

How is a site survey priced on the Mezux rate card?

Plots are charged in exactly the way routes are: by the metre of radar line actually run. Covering an area on a grid simply means adding up the lengths of all the grid lines, so the bill follows the plot size and the spacing the site needs.

  • ₹24 per metre for the standard survey of the grid.
  • ₹32 per metre for an L-section, where a service run across or along the plot also needs a depth profile of the services detected.
  • Minimum order of ₹50,000 in Delhi NCR (up to 2 km) and ₹1,00,000 elsewhere (up to 4 km). A plot needing 3 km of grid lines in Delhi NCR comes to ₹72,000 before GST.
  • ₹1,00,000 per project as the lowest bill for any plot outside Delhi NCR. Inside NCR, the minimum order is ₹50,000.
  • Volume slabs of 25%, 40% and 50% off every metre once an order passes 100 km, 500 km and 1,000 km – relevant to developers clearing many plots or a large township together.

Travel and set-up (mobilisation), any night shift, traffic control or permits, and CAD/GIS drawings each carry their own quoted price and never sit inside the metre rate. GST is added to the total. Every slab, with an online calculator, is set out on our GPR survey price list, while the GPR survey cost guide explains how a quote is built.

Who carries out the survey, and how far do crews travel?

Every site is scanned by our in-house crews on company-owned equipment. Mezux Touch runs 58 GPR systems and 18 HDD rigs from its Faridabad yard, with no hired machines and no sub-letting, and holds ISO 9001:2015, ISO 14001:2015 and ISO 45001:2018 certificates. Crews mobilise from Faridabad to plots across Delhi NCR and to other states; the same team has logged 1.5 lakh+ km of radar survey work spread over 28+ States and UTs.

For a plot in Gujarat, pre-dig work is covered on our Vadodara pre-excavation scanning page, and builders laying out new colonies can read about underground utility lines for builders.

Which guides help a site team before excavation?

STEP 1

Tell us the plot history

Share what stood on the site, when it was demolished and any old drawings, photos or borewell records you hold.

STEP 2

Send the proposed layout

The foundation or pile layout lets us tighten grid spacing where footings will sit and widen it elsewhere.

STEP 3

Receive a metre-based quote

Total grid length sets the price at ₹24 per metre, with minimums, extras and GST each shown on separate lines.

STEP 4

Scan before setting out

Our crew runs radar and EM passes across the levelled plot after demolition and before any pile point is pegged.

STEP 5

Act on the schedules

Designers review structural finds, the site team receives service marks, and flagged points are exposed by trial excavation.

Insights

Construction site GPR survey in numbers

Rate per metre by order size

Standard vs L-section GPR survey, ₹ per metre

StandardL-Section
₹0₹20₹40₹60₹80₹24₹32Up to 100 km₹18₹24100+ km₹14.4₹19.2500+ km₹12₹161,000+ km

Source: Mezux rate card, October 2026.

Standard survey cost for typical orders

Standard ₹24/m, ₹ lakh before GST, slab applied

₹0 L₹30 L₹60 L₹90 L₹120 L₹2.4 L10 km₹12 L50 km₹27 L150 km₹86.4 L600 km

Source: Mezux rate card – amounts before GST.

Our recorded output

Route surveyed, km

0 km300 km600 km900 km1200 km100 kmPeak day700 kmFastest 30 days

Source: Mezux delivery records.

Fact table

FactValueSource
Standard survey rate per metre of grid line₹24Mezux rate card
L-section survey rate per metre₹32Mezux rate card
Minimum order₹50,000 in Delhi NCR (up to 2 km); ₹1,00,000 elsewhere (up to 4 km)Mezux rate card
GPR systems owned by Mezux58Mezux records

Mobilisation, night shifts, traffic control and drawing sets are priced outside the metre rate, and GST is added.

Best prices

Get Construction Site GPR Survey at Best Prices

Price follows grid length

You pay ₹24 for every metre of radar line run across the plot, so a tighter grid only where footings sit keeps cost down.

Survey once, before setting out

Scanning the whole cleared plot in one visit costs far less than calling a crew back for spot checks ahead of the piling rig.

Bundle plots together

Developers with several sites can place them in one order, sharing mobilisation and using the minimum order more easily.

Large layouts earn slabs

Township and campus programmes above 100 km of scan lines get 25% off every metre, rising to 40% and 50% at higher totals.

Own fleet, own crews

No rented radar and no sub-letting means the quote carries no hire charge or middleman margin on top of the rate.

Extras quoted before work

Mobilisation, night work, permissions and drawing sets are listed separately on the quote, so the final bill holds no surprises.

Latest price list

Construction site GPR survey rates – Current Rates

ServiceUp to 100 kmAbove 100 km
(25% off)
Above 500 km
(40% off)
Above 1,000 km
(50% off)
Standard GPR Survey
min. order ₹50,000 NCR · ₹1,00,000 India
₹24/m₹18/m₹14.40/m₹12/m
L-Section GPR Survey
min. order ₹50,000 NCR · ₹1,00,000 India
₹32/m₹24/m₹19.20/m₹16/m

Rates per running metre of route surveyed. GST extra. Discount applies to the whole order quantity once it crosses the slab. Outside Delhi NCR the minimum order is ₹1,00,000 (covers up to 4 km). Separate from the per-metre rate: mobilisation, night shifts, traffic or permission arrangements and CAD/GIS drawings. Updated 23 October 2026.

Price range

Lowest rate₹12/mStandard, above 1,000 km
Highest rate₹32/mL-Section, up to 100 km
Minimum order₹50,000Delhi NCR (up to 2 km) · ₹1,00,000 Rest of India (up to 4 km)
FAQ

More questions about construction site GPR survey

Does a GPR site survey replace a geotechnical soil investigation?

No. Radar locates buried objects, services and voids; it does not test bearing capacity, soil strength or groundwater for foundation design. The two answer different questions and are usually commissioned together. Trial pits or boreholes at chosen findings can be added on request, but a full soil investigation remains a separate engineering task.

How is an area survey turned into a price?

We lay out a grid over the plot, choosing spacing to suit the smallest feature that matters to the design, then add up the length of every line. That total is charged at ₹24 per metre, subject to the minimum order: ₹50,000 in Delhi NCR and ₹1,00,000 outside it.

Can you survey a plot outside Delhi NCR?

Yes. Crews and equipment travel from Faridabad to sites in other states, and the trip is quoted as mobilisation. Projects outside NCR carry a ₹1,00,000 minimum order, so grouping several plots or adding a service route nearby often makes better use of the visit.

Will the ground be marked for the excavation contractor?

Yes. Detected services and the outlines of buried structures are painted or pegged on the plot as the scan proceeds, with approximate depths noted. Marks fade under rain and machine traffic, so excavation should follow soon after the survey; the signed report keeps the record once the paint has gone.

Is the survey useful for a boundary wall or drainage works?

Often, yes. Boundary walls and external drains run along the plot edge, which is exactly where incoming water, power, sewer and telecom connections cross into the site. Scanning a strip along the boundary before the trench is cut finds those connections, and the cost follows the scan length in the usual way.

What should be ready on site before the crew arrives?

The plot should be cleared and levelled as far as practical, with debris heaps and parked machinery moved off the areas to be scanned. Standing water should be drained. Tell us about locked areas, working hours and site safety rules, and keep a contact person available to show boundaries and known connection points.

When should the survey happen?

After demolition and before setting out. Earlier misses what demolition exposes; later is investigating a problem rather than preventing one.

What do you find most often?

Old footings and basement slabs, then septic tanks, soak pits, disused chambers and abandoned borewells.

Are incoming services really still live?

Frequently. Demolition rarely includes disconnection at the main, so we report services as live or unverified rather than assumed dead.

Does demolition rubble affect the survey?

Yes, it limits achievable depth. We state the figure for the site rather than quoting a general one.

Can findings be overlaid on our foundation layout?

Yes, where you provide it, as a drawing set quoted separately from the per-metre rate. Clashes are then visible rather than requiring someone to interpret two drawings together.

Get a quote

Send your plot layout for a site survey quote

What to send for an exact quote

  • Start and end points of the route, or a KML
  • District and site type
  • Survey type: standard or L-section
  • When you want the crew on site
Standard GPR₹24/m
L-Section GPR₹32/m

₹24/m · Min. order ₹50,000 — Delhi NCR (up to 2 km) · Min. order ₹1,00,000 — Rest of India (up to 4 km) · GST extra · 25–50% off above 100 km.

What happens next

  1. Scope check – we confirm route length, crossings and L-section need.
  2. Written quote – rate, slab, minimums, extras and a day-by-day programme.
  3. Mobilisation – our own crew and systems on the agreed date.

Get a Quote

Route length, location and survey type – we reply with a written quote.

Trusted by India’s telecom & infrastructure leaders

Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks
Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks