GPR Survey Timeline in Delhi NCR: How Long Does It Take?

Field days, working windows, night shifts, permissions and report issue – a practical look at what decides the length of a GPR survey programme across Delhi, Gurugram, Noida, Faridabad and Ghaziabad.

₹24/m standard₹32/m L-sectionMin 4 km · GST extra

How it works · From route file to report
HT cableWater mainOFC ductGas lineRADARGRAM
  1. STEP 1Route and windows fixed
  2. STEP 2Radar passes each shift
  3. STEP 3Finds marked on road
  4. STEP 4Signed report issued
1.5 LAKH+ KMGPR Survey Completed
58Company-Owned GPR Systems
23 YEARSUnderground Since 2003
₹24/MStandard GPR Rate · Min 4 km
Quick answer

A typical GPR survey timeline in Delhi NCR runs from one shift on site for a single plot or short street, to several days for a city cable or OFC route and a few weeks for a long corridor. Road access windows, traffic and permissions set the pace far more than the radar. Reports and drawings follow field work.

Key points
  • A GPR survey timeline has three parts: preparation, field work on site, and issue of the report.
  • In NCR, access windows, traffic and permissions take more calendar time than the scanning itself.
  • Open corridors move fastest; our best day reached 100 km with day and night shifts.
  • Crossings and HDD bore paths need tighter grids, so a few can match a kilometre of route.
  • The per-metre price stays the same however many days the work takes on site.

Updated:

Survey crew member checking a route plan on a tablet beside a radar cart
A clean route file lets scanning begin on the first morning, not after a walk-over.
Radar cart scanning a road at night under work lights
Night windows help on busy NCR roads; night working is billed separately.
Bar-chart programme showing survey shifts, crossings and report dates
Plan the survey backwards from the date excavation or boring must begin.
Signed survey report with route plan and list of detected services
The dated report outlasts paint marks and is the record to file.

How long does a GPR survey take from enquiry to report?

Ask how long does a GPR survey take and the honest reply has three parts, because every GPR survey timeline includes the time before the crew arrives, the time spent on the ground, and the time needed to issue results. Many contractors plan only for the middle part, then find that the first and last parts decide their excavation date.

  • Before field work – route files are checked, the scope and survey type are fixed, and the client arranges access with whoever owns the road.
  • Field work – radar lines and utility locating with an electromagnetic (EM) cable locator along the route, ground marking of each find and extra passes at crossings.
  • Issue of results – the signed survey report, plus CAD/GIS drawing sets or an L-section profile wherever these were ordered.

Our crews are in-house and the radar units are company-owned, sent out from the Sector 41 base in Faridabad, so no machine hire adds days at the start. In NCR most of the calendar goes on access, not on scanning. The Delhi NCR GPR survey page lists the cities and localities we cover across the region.

Why does the same route length take longer in some parts of NCR?

A radar cart moves at walking pace in every city, yet the metres it covers per shift change sharply from site to site. The usual reasons are:

  • Traffic and footfall. Markets, arterial roads and junctions often allow only short early-morning or late-night windows.
  • Crowding below ground. Older colonies and central districts hold underground utilities – power, water, sewer and telecom lines – from several owners, and tightly packed finds need closer line spacing and slower interpretation.
  • Recent large works. Delhi Metro lines, the Namo Bharat (RRTS) corridor and expressways such as the Delhi–Meerut and Dwarka Expressways have shifted services, so old records help less and more ground has to be read fresh.
  • Several road and asset owners. One route may cross MCD or NDMC roads, municipal corporation roads in Gurugram, Faridabad or Ghaziabad, and development authority land, with cables of BSES, Tata Power-DDL, DHBVN or PVVNL below. Mezux Touch is not affiliated with any of these bodies or DISCOMs. Terms differ from one owner to the next, so check with the road-owning agency early.
  • Ground and weather. Rain raises the moisture content of clay, and the resulting signal attenuation – the radar pulse losing energy in wet ground – cuts penetration depth; standing water can stop scanning on a stretch until it drains.

An open expressway shoulder or a new sector road with clear verges, on the other hand, moves quickly. The 100 km we have managed in one day came on open corridors with crews on both day and night shifts – a figure for that kind of ground, not for a crowded bazaar lane.

Which types of GPR survey job have different timelines?

Plot and site scans

A building plot, housing society compound or factory yard is scanned on a grid. Field work is short, frequently a single shift, and the report follows. Billing still starts at 4 km, so grouping several plots in one order makes sense.

City cable and OFC routes

Distribution cable and telecom duct routes along city roads are the most common NCR jobs. Their pace follows the windows on offer, and a route split between several road owners may be scanned in phases as each consent comes through.

Long corridors

Expressway-side routes, ring roads and peripheral roads allow long continuous runs and, with night shifts, the highest daily output.

Crossings and HDD bore paths

Each crossing of a road, drain or railway is scanned on a tighter grid over the intended bore line and the two pit areas. A handful of crossings can take as long as a kilometre of open route.

L-section surveys

If the work order wants the depth of each detected service plotted along the line, the ₹32 per metre L-section survey is done during the same visit. It adds some field and office time compared with a standard survey.

Which programme terms should you understand before agreeing dates?

  • Working window – the hours in which road conditions and the owner's terms let a crew scan. In central Delhi this can be just a few hours a day.
  • Output per shift – metres of route actually scanned in one window, which is different from hours spent on site.
  • Night shift – scanning after traffic thins out; it speeds up busy roads but is priced separately from the per-metre rate.
  • Mobilisation – moving crews and systems to site, also quoted as its own item.
  • Coverage – the length that was really scanned, as against stretches missed because of parked vehicles, locked gates or water.
  • Re-scan – a return visit to stretches that were blocked; on congested routes, plan for at least one.
  • Issue date – the date printed on the report. Near new metro or road works it tells the excavation team how current the data is.

What features of a survey keep the timeline short?

Several of these sit with the client, and a few sit with us.

  1. Clean route files. A KML showing the alignment, total length and every crossing lets the crew start scanning straight away instead of walking the route to understand it.
  2. Access arranged early. Traffic arrangements and permissions are outside the survey rate and are settled by the project owner with the authority concerned; a delay here pushes back everything else.
  3. Enough owned systems. With 58 GPR systems and in-house crews, a long route can be divided between teams working different stretches in parallel, subject to permissions.
  4. Radar and EM together. Pairing GPR with EM locating confirms metallic utilities in the same pass rather than on a later visit.
  5. A fixed deliverable list. Deciding at the start whether CAD/GIS sets or an L-section are needed avoids a second round of office work.

How do you plan a GPR survey timeline and budget for an NCR job?

Work backwards from the date excavation or boring has to begin:

  1. Send the route, its length and the type of work for a quote; the quote carries a programme for that route.
  2. Approach the agency that owns each stretch for access while the order is being placed.
  3. Fix survey dates against confirmed windows, putting crossings first if boring starts there.
  4. Keep excavation close behind the survey, since paint marks fade under traffic and rain.
  5. Leave time after field work for the report and any drawing sets.

The per-metre charge does not change with the number of days on site. Standard survey work is charged at ₹24 a metre, L-section work at ₹32 a metre, and no order is billed below 4 km. Inside Delhi NCR no ₹1,00,000 project minimum applies. GST, mobilisation, night working, traffic arrangements and CAD/GIS drawing sets come on top. A 6 km standard route, for instance, is ₹1,44,000 before GST and extras whether it needs two windows or six. Slabs and discounts are set out in the GPR survey price list, while city detail sits on the Gurugram and Noida pages.

What should you do with survey records after the crew leaves?

The programme does not finish when the crew leaves. Your team and the asset owners will refer to the report months later, so:

  • file the signed report, with its issue date, next to the excavation permission and work order;
  • keep the matching KML or drawing, so faded marks can be re-set from the record;
  • note every stretch the report lists as not scanned, and book a re-scan before digging there;
  • treat the record as out of date where metro or road diversions happen after the survey.

What a full deliverable set holds is explained in our article on GPR survey deliverables, and rain-season planning is covered under monsoon GPR survey in Delhi NCR.

TIP 1

Mark every crossing

Show road, drain and rail crossings on the KML so the crew schedules their closer grids from the very first day.

TIP 2

Start permissions first

Approach each road-owning agency as soon as the route is final; access is usually the longest item in the programme.

TIP 3

Share the windows

Tell us the hours each stretch can be worked, so shifts and any night working are planned around them.

TIP 4

Fix the deliverables

Decide early whether an L-section or CAD/GIS sets are needed, so office work is done once, not twice.

TIP 5

Dig soon after

Keep excavation or boring close behind the survey while ground marks are clear and nobody else has dug the verge.

FAQ

Questions about GPR survey timelines in Delhi NCR

Can a GPR survey in Delhi NCR be finished in one day?

For a single plot or a short stretch with clear access, field work often fits in one shift. Longer city routes rarely do, because working windows are short and blocked stretches need a return visit. The report is issued after field work, and any drawing set ordered with it needs further office time.

Does a night shift cut the programme in half?

Not always. Night working helps on busy roads where daytime scanning is impractical, but it depends on the road owner allowing it and on lighting and safety arrangements. Because it is charged separately from the survey rate, use it where it saves real days rather than across the whole route.

How soon after the survey should we excavate?

As soon as practical. Ground marks on NCR roads fade under traffic, rain and sweeping, and other agencies may dig the same verge in the meantime. The signed report stays the reference, but digging while marks are still clear and the ground is unchanged keeps the strike risk lowest.

Will permissions hold up the survey?

They are frequently the longest item. Scanning on a public road needs the consent of whoever owns it, and terms vary between agencies. We do not set out permit procedures for any authority; check with the road-owning agency early and pass the approved working hours to us so the dates fit them.

Does a longer programme cost more?

The survey charge itself stays per metre however long the field work runs: ₹24 for standard and ₹32 for L-section, never billed under 4 km. Night working, mobilisation, traffic arrangements and drawing sets are quoted separately, and those can change with the programme, so ask for them to be priced against your actual windows.

Can routes in several NCR cities go into one order?

Yes. Stretches in Delhi, Gurugram, Faridabad, Noida or Ghaziabad can sit in one order, each scheduled around its own access. The total length sets the discount slab, so a combined programme crosses 100 km sooner than separate orders would.

Get a quote

Send your NCR route and dates

What to send for an exact quote

  • Route drawing, KML or list of roads with start and end points
  • City / district and site type (road, estate, plant)
  • Standard survey or L-section
  • Target start date and any working-hour limits
Standard GPR₹24/m
L-Section GPR₹32/m

Minimum 4 km · GST extra · ₹1,00,000 project minimum outside Delhi NCR · 25–50% off above 100 km.

What happens next

  1. Scope check – we confirm route length, crossings and L-section need.
  2. Written quote – rate, slab, minimums, extras and a day-by-day programme.
  3. Mobilisation – our own crew and systems on the agreed date.

Get a Quote

Route length, location and survey type – we reply with a written quote.

Trusted by India’s telecom & infrastructure leaders

Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks
Bharti Airtel
Tata Communications
TCIL
Reliance Jio
Gigatel Networks
RailTel
MTNL
BSNL
Vodafone Idea
P2P Networks